This scheduled for completion by April 2019. It consists of two phases: Phase 1 is an approximately 13,500 sf building addition to be completed by October 2018 and Phase 2 is an approximately 5,000 sf remodel of the existing emergency department, scheduled to take place after occupancy of the new addition. The project is being delivered as a collaborative design/build model, with NelsonHPS managing design and construction activities. The project required intensive planning, relocating entrances and services as necessary to ensure uninterrupted operation of the facility and the Emergency Department.